Playground Renovation 2010

Playground renovation has begun! We are very excited to announce that Building Goodness Foundation and their partner AG Dillard Incorporated will be volunteering to help put in a PreSchool Play Structure and new mulch this fall.

Building Goodness Foundation and AG Dillard Incorporated will be donating their time to help renovate our playground in October/November.  We are very thankful for their help.  They will be taking all the mulch off the playground, grading the playground, putting in a new PreK play structure and then putting new mulch from Panorama Farms back on.  More details will follow in our WHAW newsletter now out, and on the website. Stay tuned!

We will chronicle our playground renovation in our fall and winter newsletters in October, November and December. These newsletters are located on the parents and staff pages.  We also have a formal detailed letter about Building Goodness Foundation and AG Dillard, also listed on the parents page.  Please check these important handouts and newsletters out!

Please check out the websites of Building Goodness Foundation and AG Dillard.  www.buildinggoodness.org and www.agdillard.com . Donate and Volunteer!!

Playground News:

  •  Special thank you to Jay Kessler, Kelly Eplee, Kathy Garstang, Mary Alice Blackwell, our WCCC board members, WCCC families, Donna Denton and Katie Moore, Richard Washington, Jim Benedict, Sandy Wilcox and WPC, for all their amazing support during this renovation!

  • Playground Project is complete!! Please see WHAW newsletter on the parents page for more details. Thank you to everyone involved in this great project!!  Thank you to Building Goodness Foundation and AG Dillard for their many hours of labor and expertise.

  • Thank you letter for WCCC about playground

  • Thank you to everyone who helped at the finale of the playground on November 13th. Thank you to:

    Wendy, Kathy Garstang, Mary Alice Blackwell, J.D. Diven, Jack Stoner, Ethan Tate, Kelly Eplee, Mike Gallahue, Greg Parrish, Kathy Garstang, Mary Alice Blackwell, Jim Benedict, Jay Stalfort, Leslie Kendrick, Micah Scharwartzman, Guian McKee, Joanna Vondrasek, Lucy Burnette, Trisha Wilburn, and Krista Birckhead.  Lindsey and John Neal, Barb Shephard, and Lucy Burnette provided food that day.

     

     

  • The playground is very close to being finished.  We had a great team here on Saturday helping install the bases for the play structure. The Building Goodness Foundation and AG Dillard volunteers as well as many of our staff and families came out to help. The designers meticulously put together the bases for the play structure.  They did a fantastic job.  We had Newsplex come out and do a piece on our playground story, and we are very thankful to Newsplex, and Stephanie Oliver for making that happen.

    We have one last final push for this Saturday the 13th of November. I will still need volunteers to come out in the around lunch time to help mulch and some in the morning to help finish putting together the play structure. 

    The BGF volunteers will start around 9am, anyone interested in helping put together the play structure, can come around then, otherwise mulchers, and lunch helpers can come around 11-12.  They will most likely work until 1pm with the installation of the play structure.

    We are very grateful for all the effort, and help these amazing volunteers have provided.  This project would not be complete without their vast knowledge on construction and design. A huge thank you to BGF, and their board members, BGF family members and staff, AG Dillard, Scott Bradshaw, and his crew, volunteer community members (Amy Mclesky, Anne Causey, Kathy Garstang, Mary Alice Blackwell), and to all the staff and parents that have helped.  A big thank you to Donna Denton, Katie Moore, Leslie Kendrick, Micah Schwartzman, Mark and Kara Chandeysson, Jeremy Spitzer, Don Long, Mike Citro, Will Abrahamson, Lucy Burnette, Christine Knight, Sandy Wilcox, Michelle Amt and Amy Ogden, Rob and Mary Cook, Jen Igo, Biff Beers, Annie Eplee, Kelly Eplee, Erica from Monticello High School, and to Ronica Turner for having some of her students come out to help. Thank you to all the families and staff that have donated food, time and money to this project.  We are very grateful for everyone's contributions. If you have any questions or inquiries; please call me at 977-3322; ext 13 or email wcccprogram@embarqmail.com.

  • Thank you to all the families and staff that donated supplies, and their time to help in the playground project on Saturday October 30th.  Everything is going really well, and we have finished all the excavation for the playground.  We layed out the landscape fabric, and mulched half of the playground.  A special thank you to Leslie Kendrick, Micah Schwartzman, Solly Schwartzman, Rob, Mary, Eli and Cyrus Cook, Don Long, Davis and Landon Long, Michelle Amt, Pooja Panta, Donna Denton, and Katie Moore for coming in and volunteering their time to help with this project.**  Thank you to the Butterfly Families for providing breakfast!
  • We are looking forward to finishing the playground project on 11/6.  We will be installing the play structure, and finishing mulching.  If you are able to volunteer, please see Ellen in the office, or email, wcccprogram@embarqmail.com.*
  • Thank you to all the staff and families that donated supplies, food and water, and their time to our playground project on 10/16, 10/23! * A special thanks to Jeremy Spitzer and family, Mark Chandeysson, Will Abrahamson, Donna Denton, Katie Moore and Kara Chandeysson for coming in and volunteering their days to help. We look forward to Saturday 10/30. Excavation will continue on the lower playground, landscape fabric will be spread and mulch will begin to be spread on top playground. We are accepting donations for lunch, takeout from Wayside, for the volunteers.  The Butterflies classroom is responsible for breakfast foods, and drinks for Saturday 10/30.  Thank you. Any questions see Ellen in the office.**

  • WCCC needs volunteers to help on Saturdays: 10/23, 10/30 and 11/6 to help with playground renovation project with Building Goodness Foundation, AG Dillard and WCCC. The tentative timeline is listed below. We need help installing landscape timbers, spreading mulch, and installing Pre-k play structure. If you are interested in helping please call or email me! wcccprogram@embarqmail.com or 977-3322; ext 13
  • Classrooms have sign up sheets for food donation for our Saturday Playground Renovation Days.  Please see your classroom sign up list for more information.  If you have any questions or want to donate please see Ellen or Michelle in the office.  Thank you!

Playground Timeline: 

  • October 16th-excavation of the upper playground, and demo of blue castle
  • Saturday, October 23rd - Dillard will continue with mulch removal and re-grading; BGF will need 4 or 5 volunteers. WCCC will probably have some additional volunteers on hand that day also.
  • Saturday, October 30th - Dillard and volunteers will spread the new mulch across the upper playground. Excavation continues on the lower playground
  • Saturday, November 6th - BGF will need volunteers to assemble the new play structure. We will need 4 to 6 BGF volunteers to accomplish this in a day. We will also continue to spread the new mulch across the playground. WCCC will probably have some additional volunteers on hand that day also.
  • Saturday, November 13th- BGF finishes installing the Pre-K play structure, and volunteers mulch lower playground
Renovation Pictures

 

Slideshow 1,DAY 1: Excavation of the Playground with AG Dillard October 16th 2010

Slideshow 2, DAY 2: October 23rd, excavation of lower playground, relocation of Toddler play structure and laying down of landscape fabric

Slideshow 3, Day 3: October 30th,
Finishing the excavation of the lower playground, laying down of the landscape fabric, and spreading of the mulch on the top playground.

Slideshow 4, Day 4: November 6th, Installation of play structure part 1

Slide Show 5, Day 5: Playground Finale

Slide Show 6, Opening Day for the playground